Historic drilling-waste pit remediation programme
All case studies
Environmental/ Central Europe

Historic drilling-waste pit remediation programme

Client: Environmental remediation contractor (named on request under NDA)

Project Overview

A mid-cycle environmental contractor was mobilising to treat a legacy pit containing weathered hydrocarbon-contaminated drill cuttings and free liquids left over from a decommissioned drilling operation. Regulatory pressure required the pit to be reduced to an inert, off-site-ready product within a defined programme.

CLIENT CHALLENGE

The Challenge

  • Highly variable feedstock — weathered cuttings, free hydrocarbons, ponded rainwater and unknown legacy chemistry.
  • Compressed regulatory timeline with penalty exposure for missed milestones.
  • Chain-of-custody documentation demanded by the asset owner and the environmental regulator.
  • Limited pad space adjacent to the pit for treatment equipment mobilisation.
ENGINEERING SOLUTION

Paragon's Approach

1

Treatment train selection exercise — dewatering, stabilisation and thermal review against a representative composite sample from across the pit.

2

Containerised dewatering unit specified around the peak expected sludge flow, with a properly sized polymer make-up skid rather than manual dosing.

3

Stabilisation mixer and chemical binder specification matched to the hydrocarbon fraction and target leachate criteria.

4

Ongoing engineering support during the treatment campaign, with sampling and analytical protocols agreed with the regulator up front.

EQUIPMENT SUPPLIED

What Paragon Supplied

  • Containerised dewatering unit (decanter, polymer make-up, feed pump)
  • Skid-mounted stabilisation mixer
  • Chemical binder supply matched to feedstock chemistry
  • Sampling and analytical protocol documentation package
RESULTS ACHIEVED

Outcomes

Pit volume reduced to inert stabilised material meeting the site's regulatory acceptance criteria.
Full chain-of-custody documentation delivered to the asset owner for handover to the regulator.
Programme completed within the regulator's defined window.
Treatment approach documented for reuse on subsequent legacy pit projects in the same permit area.
PARTNERSHIP

Delivery Partners

Where appropriate, Paragon Environmental Solutions collaborates with carefully selected OEMs, manufacturers, and technology partners to deliver the most effective solution for each project. This ensures clients receive proven equipment supported by independent engineering expertise and local operational support.

Working on a similar project?

Share the sector, region and scope — we'll come back with references and a concrete equipment or engineering recommendation within one working day.